HomeMy WebLinkAboutCOMM - Meeting Minutes - - 8-10-1937 - COMMISSIONER MINUTE BOOK
BOARD OF COUNTY COMMISSIONERS WASHINGTON COUNTY, PENNSYLVANIA
JOHN D. BERRYMAN, EARL B. AMOS. JOHN N. O'NEIL COMMISSIONERS
WARD PRINTING CO 6 1
I
Office of the County Commissioners,
Washington, Pa., August 6, 1937.
Commissioners in regular session, mwnbers present Messrs. Berryman and
Amos; Mr. O'Neil being absent.
Motion by Mr. Berryman, seconded by Mr. Amos that the County Controller
be authorized to advertise for bids for 80,000 Official Ballots more or less
and 200000 Sample Ballots more or less for use in the Primary, September 14, 1937.
Motion carried.
There being no further business the meeting was adjourned.
(S IGNE D) �J
I,
COTINTY COMMISS15VERS
Office of the County Commissioners,
Washington, Pa. , August 10, 1937.
a
Joint meeting of the County Commissioners and the County Controller for the
opening of bids for the stokers for the boilers and furnishing and installing
new thermostats in the Court House and Jail buildings and for the cleaning of
air ducts in the Court House and Jail buildings. Members present were County
Commissioners Berryman, Amos and O'Neil, and County Controller John L. Post.
The bids were opened by y the Count Controller and read in the presence of
the County Commissioners as follows :
I
BID OF MR. RALPH J. MIDGIEY, PITTSBURGH, PA.
Proposal to furnish, deliver and erect and place in successful operation at
the Court House and Jail, Washington County, Pennsylvania the following:
i
(A) Two single retort underfeed stokers, under present 150 horsepower, HRT
boilers, complete with motor driven forced draft fans, switchboard and control,
electrical wiring and steam connections, extended coal hoppers and lower section
of boiler fronts with refractory lined doors.
Excavation of pit in front of two boilers, construction of concrete walls
and floor of pit, excavation under the furnaces of two boilers, necessary repon-
struction and relining of two boiler furnaces, ash pits, and bridgewalls, in-
cluding the necessary underpinning of the present walls.
Furnishing and installing of one smoke indicator.
(B) Furnishing and installing new thermostats, replacing defective dampers,
adjusting all dampers not replaced, thoroughly overhauling and servicing all
fan, vacuum, and control equipment, including the testing of all traps and re-
placement of any defective or inadequate traps, adjusting all ill-fitting win-
' doves, testing the air delivery system, and furnishing and installing any addition-
al dampers found to be necessary to properly control and distribute the hot and
tempering air.
i
(C) Thoroughly cleaning the hot and tempering air ducts, laterals, and
risers of the entire system.
i
I
MINUTE BOOK
BOARD OF COUNTY COMMISSIONERS WASHINGTON COUNTY, PENNSYLVANIA
JOHN D. BERRYMAN, EARL B. AMOS, JOHN N. O'NEIL COMMISSIONERS
Which is deemed to describe and provide for the complete work (notwithstand-
ing that every item necessarily involved is not particularly mentioned) , all in
accordance with the attached specifications, for the sum of $11..540,, Eleven
Thousand Five Hundred Forty Dollars and to complete erection not later than 45,
Forty-Five calendar days after the award of the contract.
Segregated Prices
If not awarded the contract for the entire work (Items A to- C, inclusive) ..
the undersigned agrees to enter into a contract in' accordance with the stipula-
tions of the specifications, for one or more subdivisions of the complete works
for the following amounts :
(A) Article III, Section 1
Two single retort underfeed stokers $4924.00
Days to complete after execution of contract 36
(B) Article III, Section 2
Reconditioning of system, replacing thermo-
stats, and defective equipment 4940.00
Days to complete after execution of contract 45
(C) Article III, Section 3
Cleaning of duct system 1676.00
Days to complete after execution of contract 35
NOTE: All bidders must quote on the entire project (Items A to C, Inclusive) .
They shall be prepared to accept the entire contract., or any subdivision or
subdivisions thereof,
EXTRAS
The undersigned proposes to conduct the economy and capacity tests on one
stoker, as specified herein., should the Purchaser elect to have these tests exe-
cuted, for an additional sum of $150.00., One Hundred Fifty Dollars.
FIELD LABOR SCHEDUIE
The undersigned has based his quotation upon the following Schedule of field
labor:
Craft Man-Hours
Item A Item B Item C
Bricklayers 120
Carpenters 32 500
Cement Finishers 120
Electricians 32
Steam Fitters 110 400 100
Common Labor 100 100 400
BID OF THOMAS KING,$ PITTSBURGH, PA.
Which is deemed to describe and provide for the complete work (notwithstand-
ing that every item necessarily involved is not particularly mentioned) , all in
accordance with the attached specifications., for the sum of $12.,299,00, Twelve
Thousand Two Hundred Ninety-Nine Dollars., and to complete erection not later than
40 Forty calendar days after the award of the contract.
Segregated Prices
If not awarded the contract for the entire work (Items A to C inclusive),
the undersigned agrees to enter into a contract in accordance with the stipula-
tions of the specifications, for one or more subdivisions of the complete work,
for the following amounts :
(A) Article III,, Section I
Two single retort underfeed stokers $4,359.00
Days to complete after execution of contract 30
(B) Article III, Section 2
Reconditioning of system, replacing thermo-
stats, and defective equipment 30769.00
Dqys to complete after execution of contract 30
MINUTE BOOK
BOARD OF COUNTY COMMISSIONERS WASHINGTON COUNTY, PENNSYLVANIA
JOHN D. BERRYMAN, EARL B. AMOS, JOHN N. O'NEIL COMMISSIONERS
WARD PRINTING CO 65137
1
W Article III, Section 3 $4,171,00 '
Cleaning of duct system
i
Days to complete after execution of contract 40
i
Extras
The undersigned proposes to conduct the economy and capacity tests on one
stoker, as specified herein, should the Purchaser elect to have these tests
executed, for an additional sum of $150.000 One Hundred and Fifty Dollars.
Field Labor Schedule
The undersigned has based his quotation upon the following schedule of field
labor:
Man-Hours
Craft Item A Item B Item C
Carpenters 240
Steam Fitters 50 494
Sheet lie to 1 Workers 1600
Electricians 12
Common Labor 150
Brick Layers 200
Cement Finishers 50
i
i
BID OF WEST PENN BEATING CO. represented b
Isadore F, Levin
Which is deemed to describe and provide for the complete work (Notwithstanding
that every item necessarily involved is not particularly mentioned) , all in ac-
cordance with the attached specifications, for the sum of 12,490.00, Twelve
Thousand Four Hundred Ninety Dollars, and to complete erection not later than 30,
thirty calendar days after the award of the contract.
Segregated Prices
If not awarded the contrast for the entire work (Items A to C, inclusive),
the undersigned agrees to enter into a contract in accordance with the stipula-
tions of the specifications, for one or more subdivisions of the complete work,
for the following amounts:
(A) Article III, Section I
Two single retort underfeed stokers $6000.00
i
Days to complete after execution of contract 30
(B) Article III, Section 2
Reconditioning of system, replacing thermo-
stats, and defective equipment 5290.00
i
Days to complete after execution of contract 30, f`
I
(C) Article III, Section 3 1200.00
Cleaning of duct system j
Days to complete after execution of contract 30
Extras
i
The undersigned proposes to conduct the economy and capacity tests on one 1
stoker, as specified herein, should the Purchaser elect to have these tests exe-
cuted, for an additional sum of $100.00, One hundred Dollars.
Field Labor Schedule
The undersigned has based his q_N.otation upon the following schedule of field
labor:
Ian-Hours
Craft Item A Item C Item C
Bricklayers 80
Carpenters 400
Cement Finishers 16
Electricians 16 16
Painters 32 16
Sheet Metal Workers 24 32
_Steam Fitters 8 56
Common Laborers 200 24 72
Temp. Controllers 110
132
MINUTE BOOK
BOARD OF COUNTY COMMISSIONERS WASHINGTON COUNTY, PENNSYLVANIA
JOHN D. BERRYMAN, EARL B. AMOS, JOHN N. O'NEIL COMMISSIONERS
i
The undersigned, as bidder (s) declares that I (we) have carefully examined
the annexed plans and specifications, and have made a personal inspection of the
site of the proposed work, and that I (we ) have taken the necessary masurements
to insure that the equipment offered shall fit in the available space and shall
fully comply with the reauirements of the annexed plans and specifications.
Motion duly made and seconded that the awarding of this contract be deferred
until a later date in order that the bids may be tabulated. Motion carried.
There being no further business, the meting was Vjourned.
(SIGNED)
COUNTY COMMSIONERS
I
I
I